A Data Center Wants Your Water; Here's What A Utility Should Consider Before Moving Forward
A data center developer looking for water comes with some big decisions; potential permit changes, changing design requirements that impact supply, political traps, and more... Here's what to ask for before committing capacity and what belongs in the service agreement.
A data center developer calls a water utility with a request for two million gallons a day and a non-disclosure agreement. The general manager has a plant with four million gallons of buffer, a board that wants the tax base, and a customer base that’s fighting data center development in their community. The request is somewhere between the biggest industrial account the system has ever signed and the biggest risk it has ever taken on.
I spent years inside a large industrial’s water division and have since worked with utilities and vendors on both ends of these requests. The first number a developer gives is a permit ceiling, the cooling design behind it can change before the slab is poured, and roughly one project in five never becomes a real load. A utility that treats the request like a normal service connection ends up underwriting the developer’s uncertainty with its ratepayers’ money. This post covers what to ask for before committing capacity, how the cooling design drives the ask, and what belongs in the agreement.
I wrote about the investor side of this collision earlier this year and flagged industrial demand as one of the accelerants for 2026; this one is for the people on the supply side of the meter.
Get three numbers before anything else
Average day, peak day, and wastewater. The developer usually comes to the table with one figure, and it’s usually the ceiling on a permit application.
The permit number and the expected number are different numbers. Meta registered to consume more than 23 million gallons a day at its Richland Parish, Louisiana campus, and the company says the facility will average about 1.5 million gallons a day once it’s running in 2028, per a Congressional Research Service brief from this Summer. Google reserved 2 million gallons a day from the Western Virginia Water Authority for its Botetourt County site; the latest projection is 1.2 million. Ask for both numbers, and ask which one the developer wants to reserve; the reservation is what you’ll size the main and the plant expansion to.
Peak day is the number that breaks a system. Most new hyperscale builds run dry cooling most of the year and switch on evaporative assist during the hottest hours, so the ratio of peak day to average day runs to six or more, and a March 2026 study out of UC Riverside and Caltech measured a peaking factor of 10 across Prince William Water’s data center accounts. Microsoft’s Mount Pleasant, Wisconsin campus averages around 15,000 gallons a day and drew 468,000 on its hottest days. A campus that looks like 2% of your production on an average day can be 10% of it on the day you’d least like to find out.
Wastewater is the number nobody volunteers. On an open-loop evaporative system, 75 to 85 percent of the cooling water evaporates and the rest leaves as blowdown with concentrated salts, per Loudoun County’s summary. That blowdown goes to your sewer or needs its own discharge permit. Goodyear, Arizona capped Microsoft at 500,000 gallons a day of sewer discharge because the city’s plant had no spare capacity for industrial flows above that, and the amended development agreement had Microsoft pay $36 million toward a $90 million treatment plant expansion.
The cooling design decides the ask
The size of the request follows from the cooling design and it’s more negotiable than developers tend to volunteer. The same 100 MW of IT load can be a steady draw of several million gallons a day or a one-time fill followed by a trickle.
| Cooling approach | Water draw | Wastewater | Energy | Where you’ll see it |
|---|---|---|---|---|
| Evaporative cooling towers (open loop) | Highest. Roughly 0.5 to 2.5 MGD of peak capacity per 100 MW of IT load, above 5 MGD in hot climates | Blowdown, 15 to 25% of intake, high TDS | Lowest | Older campuses, colocation |
| Dry cooling with adiabatic assist | Low on average, large on peak days; peaking factors of 6 and up | Small | Moderate | Most new hyperscale builds |
| Closed-loop liquid cooling (direct-to-chip) | A one-time fill plus small make-up volumes | Minimal | Moderate to higher | AI training campuses |
| Air-cooled chillers | Near zero for cooling; domestic use only | Domestic only | Highest | Arizona and Texas builds after local pushback |
The closed-loop row is where the industry is heading for AI workloads. The Stargate campus in Abilene, Texas took about 8 million gallons of city water for its initial fill, per the Texas Tribune, and then, per Oracle’s fact sheet, needs roughly 12,625 gallons per building per year for maintenance. Microsoft’s fleet-wide water use effectiveness fell from 2.3 to 0.27 liters per kilowatt-hour between its 2024 and 2025 reporting, with about 90% of its owned fleet on low- or zero-water cooling, and its zero-water design has been standard for new builds since August 2024. Google’s two new Texas campuses use air cooling and draw water only for kitchens and restrooms.
That means a utility can require it. Chandler, Arizona approved a 2024 expansion only after the developer agreed to replace its water chillers with electric air cooling. Forsyth County, Georgia bars cooling systems from using the county water system outright, and Jones County requires closed-loop. The AWWA’s October 2025 white paper lists “requiring low- or zero-water cooling” among the alternatives a utility should put on the table.
One caution before you make it a condition. Water saved at the data center moves to the power plant. Lawrence Berkeley National Laboratory’s 2024 report to Congress puts the indirect water footprint of a data center’s electricity at 4.52 liters per kilowatt-hour on the national grid, about twelve times the direct on-site figure, and states the tradeoff in one sentence: air-cooled chillers use no water, but they use more energy. If your service area shares a watershed with the generating plant, zero-water cooling can be a wash. If it doesn’t, it’s a straightforward win for your system. The water and energy conversation is the same conversation, which the power utility figured out several years before the water utility did.
Who pays for the capacity
These are capacity deals and the question is who finances the capacity and who’s left holding the bag if the campus never fills.
The developer pays for what it alone will use. The Western Virginia Water Authority agreement with Google has the developer paying 100% of on-site infrastructure and a pro-rata share of off-site work, and because Google is the only customer who needs the new capacity in the early phases, it pays nearly all of it. Tucson’s proposed Project Blue would have had the developer fund more than $100 million of reclaimed water line and a 30-acre aquifer recharge facility, plus a “water positivity” charge of about $750 per acre-foot, indexed, with liquidated damages above the allocation. Meta is paying for a new treatment plant in Delhi, Louisiana so, in the mayor’s words, ratepayers aren’t affected. Those are the terms to anchor on.
The counter-example is Newton County, Georgia. Meta’s campus there accounts for about 10% of the county’s daily water use, the authority projects a supply deficit by 2030, it needs more than $250 million in upgrades, and rates rose 33% in a year against a typical 2%. The authority’s director told a reporter “We just don’t have the water.” when a later applicant asked for 9 million gallons a day, roughly the use of 30,000 households. The rate increase is what happens when the capacity gets built on the general rate base and the large user pays the same per-gallon price as everyone else.
Rate design has tools for this. A session Raftelis ran with Louisville Water at the 2026 Kentucky-Tennessee Water Professionals Conference laid out five: system development fees, stand-by or capacity reservation charges, capital recovery surcharges, take-or-pay contracts, and a high-use rate tier. Their worked example on a hypothetical $10 million expansion recovered the cost in about eight years under take-or-pay, six under a stand-by charge, and three under a high-use tier. Take-or-pay is the one to understand first: a contractual floor on billed volume that protects the utility if the campus runs at a fraction of its reservation.
Plan for the project that doesn’t happen. A 2026 Capgemini survey of more than 600 electricity executives, reported by Data Center Knowledge, found that nearly one in five data center interconnection requests never becomes real load. The power side has a rule to copy: if the developer withdraws before the utility starts construction, the cost stays with the developer; once the asset is built, it shifts to ratepayers. Prince William County, Virginia spent $1.7 million of staff time on the 2,100-acre Digital Gateway rezoning before a court voided it on a hearing-notice defect and the developer walked away. Chandler’s council rejected an AI data center last December partly because it had no named tenants; one councilmember put it as “Six years is a long time to start paying a mortgage.” Build the reservation charge so the utility is collecting from day one of the agreement, long before the first server rack arrives.
What belongs in the agreement
The AWWA and Carollo followed the white paper with a longer guide this week on evaluating data center development, and the Alliance for Water Efficiency published a primer and coordination workbook for water providers in June. Both say the same thing in different words: get it in writing, and get it before the rezoning. The experience gap I described for technology contracts is wider here; the developer’s counsel has closed dozens of these agreements and the utility is signing its first. The terms I’d insist on:
A capacity reservation with a stated maximum day. Reserve a number of gallons per day for water and a separate number for wastewater, with a reservation charge that starts at signing. The WVWA agreement reserves 2 million gallons a day of water and 570,000 of wastewater, which is a usable template.
A metered peak-day cap, with a price for exceeding it. The average-day figure in the developer’s deck protects nobody. Meter the campus daily and set a premium rate and liquidated damages above the cap, as Tucson’s draft terms did.
A cooling technology commitment. Name the cooling approach in the agreement and require the utility’s consent for a change. A campus that was permitted as closed-loop and later adds evaporative towers for a denser rack is a different customer.
Reclaimed or non-potable supply where you have it. Loudoun Water delivered more than 750 million gallons of reclaimed water to its data center customers in 2025 over a 20-mile system built for them, and allocations are at the utility’s sole discretion. If you don’t have the purple pipe, the developer can fund it, as Project Blue proposed.
Infrastructure cost allocation. On-site at 100% developer cost; off-site pro rata by capacity, with the developer paying the whole cost of anything only it needs. Replacing standard impact fees with a negotiated plant buy-in, as Goodyear did, is reasonable when the fees were never designed for a customer this size.
A take-or-pay floor. A minimum annual billed volume, or a minimum revenue amount, for the life of the agreement. This is the clause that stops the developer’s phasing risk from becoming the utility’s.
Drought and curtailment on the same terms as everyone else. The Botetourt County agreement states that drought restrictions apply to the data center the same way they apply to any other customer. Write that down; it’s the sentence the public will ask about.
Disclosure. Racine released Microsoft’s water figures only after an environmental group sued and waited 210 days; Prince William’s per-campus numbers are still behind NDAs. Utah, California, and Virginia have all passed data center water reporting laws in 2026, and Texas now denies permits to data centers that skip the state’s water survey. Put the reporting requirement in the agreement so you aren’t the one defending the secret.
Offsets counted separately from supply. Project Blue was pitched as water positive, matching 100% of its consumption through replenishment, and the Tucson council still voted unanimously to halt it. A watershed advocate’s line at the hearing was the one that stuck: “One-to-one is not sufficient, it doesn’t account for the uncertainty.” Replenishment credits are a good thing to receive. They don’t produce a gallon on the peak day, so keep them out of the capacity math.
Saying no has consequences too
After Tucson blocked Project Blue, the developer switched to air cooling, lost its reported tenant, and obtained state approval for two private wells that can draw up to 31 million gallons a year from the same aquifer the city pumps. The city got no reclaimed line, no recharge facility, no positivity charge, and no say over the draw. A refusal moves the water ask to groundwater or to the next jurisdiction; it rarely makes it disappear. Ypsilanti’s utility authority chose a 12-month moratorium on data center commitments while it studies capacity, which is a defensible middle path when two proposals could absorb the plant’s entire headroom.
Keep the scale in proportion as well. Data centers account for about 4% of Prince William Water’s supply, projected to roughly double by 2050, and the authority’s COO calls that neither a dominant share nor a radical change. Microsoft never exceeded 2.64% of West Des Moines Water Works’ pumping in any year from 2020 to 2025, and when the city imposed a lawn-watering ban in 2025 the general manager was direct that nitrates caused it, not the data centers. A well-structured data center account can be the best-paying customer a mid-sized system has ever had.
Frequently asked questions
How much water does a data center use?
It depends almost entirely on the cooling design. Across the United States, data centers directly used about 17 billion gallons in 2023, per the Congressional Research Service citing LBNL, up from 5.6 billion in 2014. Per facility, a 100 MW evaporatively cooled campus needs roughly 0.5 to 2.5 million gallons a day of peak capacity, above 5 in hot climates, while a closed-loop or air-cooled campus of the same size needs a one-time fill and then domestic volumes. Ask for the cooling design before you ask for the gallons.
Can a water utility require closed-loop or air cooling?
Yes, as a condition of service or through local ordinance. Chandler, Arizona conditioned an expansion on replacing water chillers with air cooling, Forsyth County, Georgia bars cooling from the county system, Jones County requires closed-loop, and the AWWA white paper lists low- or zero-water cooling among the standard alternatives. The tradeoff is higher electricity use and the water consumed upstream at the power plant.
Do water-positive pledges replace supply planning?
No. Google reports it replenished more than 7 billion gallons in 2025 and is targeting 120% of its consumption by 2030; Amazon says it’s 75% of the way to water positive; Microsoft replenished more than it withdrew in its last fiscal year on a global basis. Those are real programs, and none of them puts water in your clearwell on a July afternoon. Treat replenishment as a community benefit and size the system on the reservation.
What’s changing in the law?
California’s AB 2619 requires operators to give water suppliers their estimated use before a business license and report actual use on renewal, and AB 2469 requires a water supply assessment and scarcity plan for permits from 2028, with the applicant assuming the full cost of conveyance, treatment, storage, and distribution improvements, per WaterWorld’s summary. Utah’s HB 76 requires facilities using 75 acre-feet a year or more to report annually and to tell providers their anticipated use before construction. Virginia waterworks will report data center sales by category from January 2027. Texas has moved from a $500 fine for ignoring the state water survey to permit denial.
HydroKnowledge works with water utilities, and with the developers and investors across the table, on large-user agreements, demand forecasting, and the water strategy behind data center and industrial growth. If a data center request has reached your utility, get in touch before the term sheet does.